Which artifact provides the team with a view of the work and its progress?

Prepare for the EXIN Agile Scrum Master Exam. Study with flashcards and multiple-choice questions, each question includes hints and explanations. Enhance your Agile Scrum knowledge and excel in your certification exam!

The Burndown Chart serves as a vital artifact in Agile Scrum, offering a clear and visual representation of the team's work progress over time. It tracks the amount of work remaining in a sprint and illustrates how much work has been completed at any point during that sprint, providing a straightforward view of the team's pace and whether they are on track to meet their sprint goals. This ongoing visual display allows the team to assess their performance and make necessary adjustments to their workflow if needed.

In contrast, while the Sprint Backlog and the Product Backlog do provide information about tasks and features being worked on, they do not convey the same level of immediate progress insight as the Burndown Chart. The Sprint Backlog lists the work items selected from the Product Backlog for the current sprint, but it does not reflect the completion timelines. The Product Backlog focuses on the overall project scope and encompasses items that may not be scheduled for any specific sprint yet. The Definition of Done outlines the criteria required for an increment to be considered complete and does not provide progress visibility.

Thus, the Burndown Chart is the artifact that uniquely aligns with tracking the team's progress in a clear, measurable, and time-sensitive manner.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy