Which Agile event focuses on reviewing the work completed during the sprint?

Prepare for the EXIN Agile Scrum Master Exam. Study with flashcards and multiple-choice questions, each question includes hints and explanations. Enhance your Agile Scrum knowledge and excel in your certification exam!

The focus of the Sprint Review is to assess the work that has been completed during the sprint. This event takes place at the end of the sprint and involves the Scrum Team, stakeholders, and anyone else relevant to the project. The purpose is to showcase what was accomplished and to gather feedback from stakeholders, ensuring that the team's work aligns with the product vision and stakeholder expectations. During the Sprint Review, the team demonstrates the completed increments, which allows everyone to see the progress made and discuss any possible changes in direction.

This event is distinct from others like the Daily Stand-up, which is a quick, daily meeting for the team to synchronize activities and address immediate issues, and Sprint Planning, which focuses on what work will be undertaken in the upcoming sprint. The Sprint Retrospective, while also occurring at the end of a sprint, is centered on reflecting on the team's processes and finding ways to improve in the future, rather than reviewing the completed work. Hence, the Sprint Review uniquely emphasizes demonstrating and discussing the work that has been done during the sprint, making it the correct answer in this context.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy