When using planning poker for estimating story points, what should the Scrum Master ensure?

Prepare for the EXIN Agile Scrum Master Exam. Study with flashcards and multiple-choice questions, each question includes hints and explanations. Enhance your Agile Scrum knowledge and excel in your certification exam!

In the context of using planning poker for estimating story points, it is essential for the Scrum Master to ensure that consensus includes the entire work involved from all perspectives. This approach fosters collaboration and comprehensive understanding among team members, as it integrates insights from different roles within the team, such as developers, testers, and business analysts.

Reaching a consensus allows the team to collectively assess the complexity and effort required for a user story. Involving diverse perspectives ensures that no critical aspects are overlooked, which enhances the accuracy and reliability of the estimates. This collective approach also promotes engagement among team members, encouraging open communication and shared ownership of the project work.

In contrast, estimating only from a development perspective might lead to an incomplete understanding of the user story, neglecting factors such as testing or user experience, which are crucial for delivering a high-quality product. Therefore, ensuring consensus that incorporates various perspectives aligns with Agile principles and improves overall team performance.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy