When a scrum team is unsure about the sprint length, what should the scrum master advise?

Prepare for the EXIN Agile Scrum Master Exam. Study with flashcards and multiple-choice questions, each question includes hints and explanations. Enhance your Agile Scrum knowledge and excel in your certification exam!

In situations where a Scrum team is uncertain about the appropriate sprint length, the most effective approach is to consider the stability of the backlog. By basing the sprint length on backlog stability, the team can ensure that they have a well-defined set of requirements and tasks to work on. When the backlog is stable, it allows the team to commit to a defined amount of work for the duration of the sprint, leading to more predictable outcomes and maintainable pace.

A focus on backlog stability encourages the team to analyze how frequently items are changing and ensures that they can deliver a potentially releasable product increment at the end of each sprint. If the backlog is in flux, opting for a longer sprint could lead to wasted time and effort as priorities shift. Hence, aligning the length of the sprint with the stability of the backlog can promote better results.

Experimenting with different sprint lengths can be beneficial, but it should primarily be done when the team is more familiar with their workflow and practices. Simply relying on longer sprints for the sake of thorough planning can lead to delays and missed opportunities for feedback. Consistency without variation does not allow for adaptation and improvement, which are central to the Agile methodology. Therefore, considering the stability of the backlog provides a foundation for

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy