If the burndown chart shows a bar extending below the X-axis, what does this indicate?

Prepare for the EXIN Agile Scrum Master Exam. Study with flashcards and multiple-choice questions, each question includes hints and explanations. Enhance your Agile Scrum knowledge and excel in your certification exam!

When a burndown chart shows a bar extending below the X-axis, this signifies that the total work remaining in the sprint or the project has decreased below the initial amount of work planned. This scenario typically indicates that the project scope has been extended, possibly due to additional work items or user stories being added after the sprint planning.

In Agile and Scrum practices, the burndown chart is a visual representation of the work left to do versus time. Ideally, the chart should trend downward as tasks are completed. When it dips below the X-axis, it suggests that new tasks have been added or previously completed tasks have been re-evaluated, altering the overall sprint workload. This is a key indicator that needs attention, as it can affect the team's potential to complete work within the sprint timeframe.

In contrast to other options, such as indicating the project is ahead of schedule, showing issues with the team's velocity, or suggesting that the sprint is almost complete, the presence of bars below the X-axis specifically reflects a change or addition to the scope of work, rather than the completion status or performance metrics alone.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy