If a team member is not performing as expected in a scrum team, who should take action?

Prepare for the EXIN Agile Scrum Master Exam. Study with flashcards and multiple-choice questions, each question includes hints and explanations. Enhance your Agile Scrum knowledge and excel in your certification exam!

In a Scrum team, addressing underperformance is a collective responsibility. While a reporting manager traditionally manages performance issues, in the context of Scrum, the most effective approach involves collaboration and communication within the team.

The Scrum Master plays a crucial role in facilitating discussions and helping the team navigate challenges, but they are not responsible for personnel management in the same way a reporting manager would be. The Product Owner focuses on the product backlog and prioritization, which does not directly address individual performance issues. The entire team has a vested interest in each member's contributions, and they should support one another, offering help and feedback to improve team effectiveness.

In summary, while the reporting manager might typically have a formal role in addressing underperformance, Scrum encourages a more integrated approach where the team collectively supports each member, creating an environment for growth and accountability. This aligns with Scrum principles that emphasize collaboration, teamwork, and shared responsibility for outcomes.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy