During which Scrum event is the team expected to demonstrate their work to stakeholders?

Prepare for the EXIN Agile Scrum Master Exam. Study with flashcards and multiple-choice questions, each question includes hints and explanations. Enhance your Agile Scrum knowledge and excel in your certification exam!

The team is expected to demonstrate their work to stakeholders during the Sprint Review. This event occurs at the end of each sprint and serves the purpose of providing a platform for the team to showcase the completed work, in alignment with the predefined Sprint Goal. Stakeholders are invited to attend the Sprint Review, and their feedback is valuable for refining the product and ensuring that it meets customer expectations.

During this event, the team presents the Increment—what has been built or achieved during the sprint. This allows for an interactive discussion, where team members can highlight the features and functionalities developed, while stakeholders can ask questions and provide input. This collaboration helps foster transparency and engagement between the development team and stakeholders, which is central to the agile philosophy of adaptive planning and continual improvement.

In contrast, the other events serve different purposes. Sprint Planning is focused on defining the work for the upcoming sprint, the Daily Scrum is a brief check-in for team members to synchronize their activities and plan for the day, and the Sprint Retrospective is a reflective meeting aimed at discussing what went well and what could be improved in the team's processes. None of these events include the demonstration aspect that is pivotal in the Sprint Review.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy