As a scrum master, how should you respond to a team member who prefers time estimates over story points?

Prepare for the EXIN Agile Scrum Master Exam. Study with flashcards and multiple-choice questions, each question includes hints and explanations. Enhance your Agile Scrum knowledge and excel in your certification exam!

In addressing a team member's preference for time estimates over story points, it is essential to emphasize that estimates play a critical role in the team's ability to plan and execute effectively, regardless of the specific method used. The primary goal of estimation in Agile is to facilitate team planning by providing a way to quantify the effort and complexity involved in delivering work items.

By explaining that estimates are intended for team planning, you can help the team member understand that while they have a preference for time estimates, the use of story points may better capture the relative complexity and effort involved in the work. Story points offer a more abstract way to estimate work, allowing teams to consider factors beyond simple time duration, such as uncertainty and effort. This understanding fosters an environment where the team can collaborate and align on methods that best serve their collective workflow and goals.

This approach also promotes flexibility and encourages open dialogue within the team, allowing for a conversation on how best to balance different estimation methods while focusing on achieving shared outcomes in project planning and delivery.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy